Panther Installation

  1. ClosedPanther Site Assessment Form
    • Confirm the Site Assessment Form [AW-19118] has been accurately completed and any open items have been addressed.
  2. ClosedPanther System Installation Qualification and Operational Qualification Checklist
  3. ClosedUncrating the Panther System
    1. Uncrating the Panther System
    2. Uncrating the Accessory Kit
    3. Uncrating the Marketing Kit
  4. ClosedInstallation Qualification (IQ)
    1. Move and place the Instrument at the customer’s specified location as per the Site Assessment Form.
    2. UPS Installation
    3. Monitor Installation
    4. PC Hardware Setup
    5. Software Installation
    6. Initial Module Preparation/Extra HW Installation
    7. Run Instrument Setup (Firmware)
    8. Panels and Canopy Installation
    9. System Leveling
    10. Trims and Door Panel Assembly
    11. Install the Front Marketing Panel
    12. Barcode Scanner Bracket Installation
    13. Hand-Held Barcode Scanner
    14. Verify Fittings are Hand Tight
    15. Pipettor Auto-Teaching
    16. Load Service Software Customer Parameters.
    17. Check Lumo Cal Factor
      1. If the Lumo Cal Factor is within specification, proceed to the next step.
        To be within specifications, the Calibration Factor MUST read between 0.12–0.24.
      2. If Lumo Cal Factor is NOT within specification, (e.g. Cal Factor is set to 1), then run Syscheck (during OQ)
    18. Teach the Linear Distributor
      1. Distributor Teaching without the IQ Auto Teach Tool (for System SW v5.3 and below)
      2. Distributor Teaching with the IQ Auto Teach Tool (for System SW v6.2 and above)
    19. Fill the Cooling Module
    20. Configure the Reagent and Sample Bay Barcode Scanners
    21. Install the Pipettor Front Shield
    22. Printer Installation
  5. Firewall and Network Connections (if needed)
  6. ClosedOperational Qualification (OQ)
    1. Pipettor Pressure Integrity Test
    2. System Level Operational Qualification (OQ)
    3. System Bootup
    4. Panther GUI SW Configuration
    5. Software Verification
    6. System Prime
    7. Check Lumo Cal Factor
      1. To be within specifications, the Calibration Factor MUST read between 0.12–0.24
        If the Lumo Cal Factor is within specification, proceed to Step8.
      2. If Lumo Cal Factor is NOT within specification, (e.g. Cal Factor is set to 1), then run SysCheck.

      Note— If Lumo Cal Factor is already confirmed, skip to Step 8.

    8. Panther Luminometer Flashcheck Reagent Verification Procedure
  7. Panther System Performance Qualification (PQ) Procedure
  8. ClosedPost Qualification
    1. Dispose of universal fluids according to laboratory procedures.
    2. Empty solid and liquid waste according to laboratory procedures.